Dept. of Trans. PROGRESS Serial No. Contract No. 16-050-12-34 11-002704 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 70% Location: Federal Project: 11-SD-5-R19.9/R21.2 IIMD-051(613) HPLU-6211(105) Progress payment No. 022 Payment period ending: 02-20-16 L B CIVIL CONSTRUCTION INC 11585 SORRENTO VALLEY RD #104 SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,872,133.07 12,700.00 2. a. Extra Work 491,540.83 46,897.83 b. Adustment Comp. 613,706.15 -22,989.75 3. Materials on Hand 4. Earned Subject to Retention 6,977,380.05 36,608.08 5. Mobilization 200,000.00 0.00 6. Total Work Completed 7,177,380.05 7. Deductions -4,135.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,173,245.05 38,608.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,608.08