Dept. of Trans. PROGRESS Serial No. Contract No. 16-142-15-09 11-002704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 77% Location: Federal Project: 11-SD-5-R19.9/R21.2 IIMD-051(613) HPLU-6211(105) Progress payment No. 025 Payment period ending: 05-20-16 L B CIVIL CONSTRUCTION INC 11585 SORRENTO VALLEY RD #104 SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,896,698.07 7,600.00 2. a. Extra Work 539,632.68 24,299.65 b. Adustment Comp. 605,666.15 -8,040.00 3. Materials on Hand 4. Earned Subject to Retention 7,041,996.90 23,859.65 5. Mobilization 200,000.00 0.00 6. Total Work Completed 7,241,996.90 7. Deductions -4,135.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,237,861.90 21,859.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,859.65