Dept. of Trans. PROGRESS Serial No. Contract No. 16-235-16-03 11-002714 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 8% Location: Federal Project: 11-SD-5-R20.3/R21.4 STPI-005-1(631) Progress payment No. 002 Payment period ending: 08-20-16 CLEAN CUT LANDSCAPE 8406 N ARMSTRONG CLOVIS CA 93619 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 37,183.54 35,283.54 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 37,183.54 35,283.54 5. Mobilization 20,134.50 20,134.50 6. Total Work Completed 57,318.04 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 57,318.04 55,418.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,418.04