Dept. of Trans. PROGRESS Serial No. Contract No. 16-264-15-38 11-002714 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 10% Location: Federal Project: 11-SD-5-R20.3/R21.4 STPI-005-1(631) Progress payment No. 003 Payment period ending: 09-20-16 CLEAN CUT LANDSCAPE 8406 N ARMSTRONG CLOVIS CA 93619 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 124,879.09 87,695.56 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 124,879.09 87,695.56 5. Mobilization 30,201.75 10,067.25 6. Total Work Completed 155,080.84 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 152,080.84 94,762.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 94,762.81