Dept. of Trans. PROGRESS Serial No. Contract No. 18-022-15-16 11-002714 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 47% Location: Federal Project: 11-SD-5-R20.3/R21.4 STPI-005-1(631) Progress payment No. 019 Payment period ending: 01-20-18 CLEAN CUT LANDSCAPE INCORPORATED 7726 N FIRST ST UNIT 137 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 636,535.32 3,617.91 2. a. Extra Work 12,408.02 0.00 b. Adustment Comp. 6,617.23 0.00 3. Materials on Hand 4. Earned Subject to Retention 655,560.57 3,617.91 5. Mobilization 40,269.00 0.00 6. Total Work Completed 695,829.57 7. Deductions -37,200.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 658,629.57 3,617.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,617.91