Dept. of Trans. PROGRESS Serial No. Contract No. 18-264-11-56 11-002714 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 67% Location: Federal Project: 11-SD-5-R20.3/R21.4 STPI-005-1(631) Progress payment No. 026 Payment period ending: 09-20-18 CLEAN CUT LANDSCAPE INCORPORATED 7726 N FIRST ST UNIT 137 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 666,592.76 6,053.09 2. a. Extra Work 12,408.02 0.00 b. Adustment Comp. 6,617.23 0.00 3. Materials on Hand 4. Earned Subject to Retention 685,618.01 6,053.09 5. Mobilization 40,269.00 0.00 6. Total Work Completed 725,887.01 7. Deductions -36,200.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 689,687.01 6,053.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,053.09