Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-288-08-19 11-002714 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-5-R20.3/R21.4 STPI-005-1(631) Progress payment No. 041 Payment period ending: 01-08-20 CLEAN CUT LANDSCAPE INCORPORATED 1865 HERNDON AVE #K591 CLOVIS CA 93611 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 722,732.88 -8,800.00 2. a. Extra Work 12,408.02 0.00 b. Adustment Comp. 6,617.23 0.00 3. Materials on Hand 4. Earned Subject to Retention 741,758.13 -8,800.00 5. Mobilization 40,269.00 0.00 6. Total Work Completed 782,027.13 7. Deductions -105,195.85 -41,495.85 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 676,831.28 -50,295.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -50,295.85