Dept. of Trans. PROGRESS Serial No. Contract No. 06-143-13-47 11-003204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 99% 11-SD-78-1.7/2.3 Federal Project: ACNH-P078(105) Progress payment No. 07 Payment period ending: 05-20-06 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 839,436.22 102,324.15 2.a. Extra Work 31,595.06 14,698.89 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 871,031.28 117,023.04 5. Mobilization 100,000.00 0.00 6. Total Work Completed 971,031.28 7. Deductions -375.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 970,656.28 117,023.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 117,023.04