Dept. of Trans. PROGRESS Serial No. Contract No. 09-022-13-55 11-003504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 22% 11-SD-94-8.3/8.7 Federal Project: STPL-6211(49) Progress payment No. 02 Payment period ending: 01-20-09 WESTERN RIM CONSTRUCTORS INC 912 S ANDREASEN DRIVE STE 108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 98,948.95 47,411.97 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 98,948.95 47,411.97 5. Mobilization 36,293.11 0.00 6. Total Work Completed 135,242.06 7. Deductions -41.58 -41.58 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 135,200.48 47,370.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 47,370.39