Dept. of Trans. PROGRESS Serial No. Contract No. 08-142-14-35 11-010614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 12% 11-SD-52-14.1/16.3 Federal Project: NONE Progress payment No. 05 Payment period ending: 05-20-08 ERRECAS INC P O BOX 640 LAKESIDE CA 92040 Escrow No. 02360 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,863,477.74 3,182,681.03 2.a. Extra Work 2,311,399.31 518,935.12 b. Adjustment Comp. -208,166.00 -208,166.00 3. Materials on Hand 677,301.99 142,586.46 4. Earned Subject to Retention 11,644,013.04 3,636,036.61 5. Mobilization 2,261,000.00 476,000.00 6. Total Work Completed 13,227,711.05 7. Deductions -10,000.00 20,000.00 8. a.Contract Retentions -1,153,700.81 -352,903.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,741,312.23 3,779,133.44 10. Reduction Amt to Escrow 11. Payment to Escrow 1,153,700.00 12. Net Pymt. this Estimate 3,779,133.44