Dept. of Trans. PROGRESS Serial No. Contract No. 09-236-13-52 11-010614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 52% 11-SD-52-14.1/16.3 Federal Project: NONE Progress payment No. 20 Payment period ending: 08-20-09 ERRECAS INC P O BOX 640 LAKESIDE CA 92040 Escrow No. 02360 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,103,842.73 1,063,558.07 2.a. Extra Work 4,780,442.15 13,398.12 b. Adjustment Comp. -406,315.69 0.00 3. Materials on Hand 661,844.32 -18,855.99 4. Earned Subject to Retention 37,139,813.51 1,058,100.20 5. Mobilization 2,380,000.00 0.00 6. Total Work Completed 38,857,969.19 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -1,856,990.68 -52,905.01 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 37,652,822.83 995,195.19 10. Reduction Amt to Escrow 11. Payment to Escrow 1,856,990.00 12. Net Pymt. this Estimate 995,195.19