Dept. of Trans. PROGRESS Serial No. Contract No. 10-026-07-14 11-010614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 66% 11-SD-52-14.1/16.3 Federal Project: NONE Progress payment No. 25 Payment period ending: 01-20-10 ERRECAS INC P O BOX 640 LAKESIDE CA 92040 Escrow No. 02360 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,623,529.98 285,472.78 2.a. Extra Work 4,998,567.04 45,283.73 b. Adjustment Comp. -373,707.33 4,343.40 3. Materials on Hand 501,912.30 -83,092.12 4. Earned Subject to Retention 41,750,301.99 252,007.79 5. Mobilization 2,380,000.00 0.00 6. Total Work Completed 43,628,389.69 7. Deductions -25,000.00 -5,000.00 8. a.Contract Retentions -2,087,515.10 -12,600.39 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 42,017,786.89 234,407.40 10. Reduction Amt to Escrow 11. Payment to Escrow 2,087,510.00 12. Net Pymt. this Estimate 234,407.40