Dept. of Trans. PROGRESS Serial No. Contract No. 10-082-14-58 11-010614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 70% 11-SD-52-14.1/16.3 Federal Project: NONE Progress payment No. 27 Payment period ending: 03-30-10 ERRECAS INC P O BOX 640 LAKESIDE CA 92040 Escrow No. 02360 Total Estimate This Estimate 1. Contract Itms Without Mobil. 37,011,740.56 175,599.69 2.a. Extra Work 5,258,038.76 169,216.67 b. Adjustment Comp. -373,707.33 0.00 3. Materials on Hand 530,685.21 28,772.91 4. Earned Subject to Retention 42,426,757.20 373,589.27 5. Mobilization 2,380,000.00 0.00 6. Total Work Completed 44,276,071.99 7. Deductions -1,000.00 10,000.00 8. a.Contract Retentions -2,121,337.86 -18,679.46 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 42,684,419.34 364,909.81 10. Reduction Amt to Escrow 11. Payment to Escrow 2,121,330.00 12. Net Pymt. this Estimate 364,909.81