Dept. of Trans. PROGRESS Serial No. Contract No. 10-112-09-08 11-010614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 73% 11-SD-52-14.1/16.3 Federal Project: NONE Progress payment No. 28 Payment period ending: 04-20-10 ERRECAS INC P O BOX 640 LAKESIDE CA 92040 Escrow No. 02360 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,500,011.29 1,488,270.73 2.a. Extra Work 5,274,970.89 16,932.13 b. Adjustment Comp. -312,152.20 61,555.13 3. Materials on Hand 526,368.89 -4,316.32 4. Earned Subject to Retention 43,989,198.87 1,562,441.67 5. Mobilization 2,380,000.00 0.00 6. Total Work Completed 45,842,829.98 7. Deductions -4,000.00 -3,000.00 8. a.Contract Retentions -2,199,459.94 -78,122.08 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 44,165,738.93 1,481,319.59 10. Reduction Amt to Escrow 11. Payment to Escrow 2,199,450.00 12. Net Pymt. this Estimate 1,481,319.59