Dept. of Trans. PROGRESS Serial No. Contract No. 10-264-13-47 11-010614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-52-14.1/16.3 Federal Project: NONE Progress payment No. 33 Payment period ending: 09-20-10 ERRECAS INC P O BOX 640 LAKESIDE CA 92040 Escrow No. 02360 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,758,711.06 861,556.77 2.a. Extra Work 5,469,315.61 26,929.70 b. Adjustment Comp. -276,482.52 -85,293.64 3. Materials on Hand 350,009.08 0.00 4. Earned Subject to Retention 50,301,553.23 803,192.83 5. Mobilization 2,380,000.00 0.00 6. Total Work Completed 52,331,544.15 7. Deductions -3,000.00 4,000.00 8. a.Contract Retentions -2,515,077.66 -40,159.64 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 50,163,475.57 767,033.19 10. Reduction Amt to Escrow 11. Payment to Escrow 2,515,070.00 12. Net Pymt. this Estimate 767,033.19