Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-06-12 11-0223U4 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 1% Location: Federal Project: 11-SD-5-R29.1/R30.5 NHPI-051(625) HPLU-6211(119) Progress payment No. 002 Payment period ending: 03-20-15 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 590,177.12 550,531.12 2. a. Extra Work 149,524.77 6,977.19 b. Adustment Comp. -42,817.88 0.00 3. Materials on Hand 4. Earned Subject to Retention 696,884.01 557,508.31 5. Mobilization 6. Total Work Completed 696,884.01 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 691,884.01 552,508.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 552,508.31