Dept. of Trans. PROGRESS Serial No. Contract No. 16-021-16-31 11-0223U4 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 22% Location: Federal Project: 11-SD-5-R29.1/R30.5 NHPI-051(625) HPLU-6211(119) Progress payment No. 014 Payment period ending: 01-20-16 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,774,337.16 1,624,220.43 2. a. Extra Work 327,905.55 29,063.40 b. Adustment Comp. -41,483.88 1,334.00 3. Materials on Hand 753,294.39 -208,366.51 4. Earned Subject to Retention 16,814,053.22 1,446,251.32 5. Mobilization 5,424,500.52 0.00 6. Total Work Completed 21,485,259.35 7. Deductions -21,780.00 -10,260.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,216,773.74 1,435,991.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,435,991.32