Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-109-07-15 11-0301U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-5-R28.3/R37.0 Federal Project: ACIM-X073(59) STPL-6066(39) Progress payment No. 80 Payment period ending: 08-07-08 E L YEAGER CONSTRUCTION COMPANY INC 1995 AGUA MANSA RD RIVERSIDE CA 925092405 Escrow No. 01913 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,319,243.48 191,577.00 2.a. Extra Work 20,962,847.51 13,446.10 b. Adjustment Comp. 10,941,234.68 35,042.54 3. Materials on Hand 4. Earned Subject to Retention 132,223,325.67 240,065.64 5. Mobilization 9,500,000.00 0.00 6. Total Work Completed 141,723,325.67 7. Deductions -631,269.46 -171,577.00 8. a.Contract Retentions -6,607,031.95 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 6,607,031.95 0.00 9. Total pay to Contractor 141,092,056.21 68,488.64 10. Reduction Amt to Escrow -6,607,030.00 0.00 11. Payment to Escrow 6,607,030.00 12. Net Pymt. this Estimate 68,488.64