Dept. of Trans. PROGRESS Serial No. Contract No. 01-355-14-32 11-0479K4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 14% 11-SD-5-8.6/9.4 Federal Project: CML-6066(34) Progress payment No. 03 Payment period ending: 12-20-01 T M ENGINEERING 19301 VENTURA BLVD STE 200 TARZANA CA 91356 Escrow No. 01836 Total Estimate This Estimate 1. Contract Itms Without Mobil. 441,735.54 150,106.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 441,735.54 150,106.50 5. Mobilization 337,500.00 112,500.00 6. Total Work Completed 779,235.54 7. Deductions -21,981.47 -3,993.82 8. a.Contract Retentions -44,173.55 -15,010.65 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 713,080.52 243,602.03 10. Reduction Amt to Escrow 11. Payment to Escrow 44,170.00 12. Net Pymt. this Estimate 243,602.03