Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-06-14 11-056324 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 40% Location: Federal Project: 11-SD-11-0.0/1.6 NONE Progress payment No. 016 Payment period ending: 03-20-15 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA STE 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,994,472.81 1,570,794.66 2. a. Extra Work 673,446.52 12,424.63 b. Adustment Comp. 117,352.03 0.00 3. Materials on Hand 228,143.10 1,663.10 4. Earned Subject to Retention 30,013,414.46 1,584,882.39 5. Mobilization 4,962,190.30 0.00 6. Total Work Completed 34,747,461.66 7. Deductions -16,049.71 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 34,959,555.05 1,578,882.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,578,882.39