Dept. of Trans. PROGRESS Serial No. Contract No. 15-236-16-12 11-056324 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 55% Location: Federal Project: 11-SD-11-0.0/1.6 NONE Progress payment No. 022 Payment period ending: 08-20-15 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA STE 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,879,568.24 659,508.68 2. a. Extra Work 988,080.67 34,402.85 b. Adustment Comp. 305,352.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 41,173,000.94 693,911.53 5. Mobilization 4,962,190.30 0.00 6. Total Work Completed 46,135,191.24 7. Deductions -20,481.53 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 46,114,709.71 689,911.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 689,911.53