Dept. of Trans. PROGRESS Serial No. Contract No. 15-302-11-38 11-056324 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 59% Location: Federal Project: 11-SD-11-0.0/1.6 NONE Progress payment No. 024 Payment period ending: 10-20-15 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA STE 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,915,133.38 1,514,965.34 2. a. Extra Work 1,043,564.59 34,721.09 b. Adustment Comp. 835,450.56 530,098.53 3. Materials on Hand 4. Earned Subject to Retention 44,794,148.53 2,079,784.96 5. Mobilization 4,962,190.30 0.00 6. Total Work Completed 49,756,338.83 7. Deductions -21,481.53 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 49,734,857.30 2,078,784.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,078,784.96