Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-138-10-46 11-056394 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-11-2.7/2.7 ACCB-P011(9) Progress payment No. 019 Payment period ending: 04-16-24 RAL INVESTMENT 10065 OLD GROVE RD #200 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,825,422.65 25,582.45 2. a. Extra Work 2,173,872.87 232,830.73 b. Adustment Comp. 2,573,787.90 0.00 3. Materials on Hand 4. Earned Subject to Retention 15,573,083.42 258,413.18 5. Mobilization 1,906,289.02 0.00 6. Total Work Completed 17,479,372.44 7. Deductions -60,727.16 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,418,645.28 258,413.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 258,413.18