Dept. of Trans. PROGRESS Serial No. Contract No. 10-026-07-14 11-063804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 6% 11-SD-8-17.4/R18.7 Federal Project: ACIM-081(302) Progress payment No. 02 Payment period ending: 01-20-10 SIM J HARRIS INC 9685 VIA EXCELENCIA SUITE 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 460,077.55 331,723.05 2.a. Extra Work 53,922.50 53,922.50 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 514,000.05 385,645.55 5. Mobilization 419,014.40 419,014.40 6. Total Work Completed 933,014.45 7. Deductions -11,764.40 -11,764.40 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 921,250.05 792,895.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 792,895.55