Dept. of Trans. PROGRESS Serial No. Contract No. 13-353-15-45 11-063814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 79% 11-SD-8-17.4/R18.7 Federal Project: ACIM-081(312) Progress payment No. 05 Payment period ending: 12-20-13 PACIFIC RESTORATION GROUP INC P O BOX 429 PERRIS CA 92572 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 729,249.19 140,589.58 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 729,249.19 140,589.58 5. Mobilization 65,000.00 3,250.00 6. Total Work Completed 794,249.19 7. Deductions -1,000.00 11,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 793,249.19 154,839.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 154,839.58