Dept. of Trans. PROGRESS Serial No. Contract No. 04-145-13-30 11-064904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 43% 11-SD-15-R6.4/R7.5 Federal Project: ACNH-015-4(189) I-015-4(189) Progress payment No. 08 Payment period ending: 05-20-04 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920838831 Escrow No. 02146 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,345,034.30 156,723.48 2.a. Extra Work 69,037.77 53,484.35 b. Adjustment Comp. 3. Materials on Hand 37,238.72 37,238.72 4. Earned Subject to Retention 1,451,310.79 247,446.55 5. Mobilization 510,150.00 0.00 6. Total Work Completed 1,924,222.07 7. Deductions -10,200.00 20,000.00 8. a.Contract Retentions -109,385.36 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,841,875.43 267,446.55 10. Reduction Amt to Escrow 11. Payment to Escrow 109,380.00 12. Net Pymt. this Estimate 267,446.55