Dept. of Trans. PROGRESS Serial No. Contract No. 04-237-12-56 11-068004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 46% 11-IMP-7-1.1/7.0 Federal Project: ACIM-008-2(99) ACIM-008-2(99) ACST-X025(26) Progress payment No. 08 Payment period ending: 08-20-04 COFFMAN SPECIALTIES INC 4375 JUTLAND DRIVE STE 260 SAN DIEGO CA 92117 Escrow No. 02162 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,166,895.43 2,462,164.87 2.a. Extra Work 283,001.35 50,778.29 b. Adjustment Comp. 50,592.46 0.00 3. Materials on Hand 17,691.45 10,101.67 4. Earned Subject to Retention 10,518,180.69 2,523,044.83 5. Mobilization 2,915,229.85 0.00 6. Total Work Completed 13,415,719.09 7. Deductions -40,800.00 -10,800.00 8. a.Contract Retentions -596,805.19 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,795,805.35 2,512,244.83 10. Reduction Amt to Escrow 11. Payment to Escrow 596,800.00 12. Net Pymt. this Estimate 2,512,244.83