Dept. of Trans. PROGRESS Serial No. Contract No. 04-357-12-51 11-068004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 76% 11-IMP-7-1.1/7.0 Federal Project: ACIM-008-2(99) ACIM-008-2(99) ACST-X025(26) Progress payment No. 12 Payment period ending: 12-20-04 COFFMAN SPECIALTIES INC 4375 JUTLAND DRIVE STE 260 SAN DIEGO CA 92117 Escrow No. 02162 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,218,159.68 1,578,015.82 2.a. Extra Work 350,280.48 1,796.23 b. Adjustment Comp. 324,360.57 34,675.17 3. Materials on Hand 105,709.34 -8,146.45 4. Earned Subject to Retention 16,998,510.07 1,606,340.77 5. Mobilization 3,068,663.00 153,433.15 6. Total Work Completed 19,961,463.73 7. Deductions -743,422.08 -383,359.96 8. a.Contract Retentions -849,925.50 -80,317.03 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,473,825.49 1,296,096.93 10. Reduction Amt to Escrow 11. Payment to Escrow 849,920.00 12. Net Pymt. this Estimate 1,296,096.93