Dept. of Trans. PROGRESS Serial No. Contract No. 08-053-14-30 11-068024 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 3% 11-IMP-7-3.7/6.9 Federal Project: NONE Progress payment No. 01 Payment period ending: 02-20-08 SIERRA LANDSCAPE CO 73 771 DINAH SHORE DR STE 200 PALM DESERT CA 92211 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 88,354.00 88,354.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 88,354.00 88,354.00 5. Mobilization 39,100.00 39,100.00 6. Total Work Completed 127,454.00 7. Deductions -8,835.40 -8,835.40 8. a.Contract Retentions -8,835.40 -8,835.40 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 109,783.20 109,783.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 109,783.20