Dept. of Trans. PROGRESS Serial No. Contract No. 02-144-12-45 11-069104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 24% 11-SD-5-R19.4/R20.1 Federal Project: ACNH-X073(58) Progress payment No. 07 Payment period ending: 05-20-02 MARINA LANDSCAPE INC 1100 E KATELLA AVE ANAHEIM CA 92805 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 769,257.16 254,845.56 2.a. Extra Work 13,465.60 -1,699.12 b. Adjustment Comp. 6,549.00 6,549.00 3. Materials on Hand 10,303.06 10,303.06 4. Earned Subject to Retention 799,574.82 269,998.50 5. Mobilization 42,750.00 0.00 6. Total Work Completed 832,021.76 7. Deductions -32,242.95 -10,000.00 8. a.Contract Retentions -56,098.69 -3,141.06 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 753,983.18 256,857.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 256,857.44