Dept. of Trans. PROGRESS Serial No. Contract No. 02-168-14-18 11-069104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 28% 11-SD-5-R19.4/R20.1 Federal Project: ACNH-X073(58) Progress payment No. 08 Payment period ending: 06-20-02 MARINA LANDSCAPE INC 1100 E KATELLA AVE ANAHEIM CA 92805 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 948,596.80 179,339.64 2.a. Extra Work 19,431.42 5,965.82 b. Adjustment Comp. 9,452.56 2,903.56 3. Materials on Hand 24,277.16 13,974.10 4. Earned Subject to Retention 1,001,757.94 202,183.12 5. Mobilization 42,750.00 0.00 6. Total Work Completed 1,020,230.78 7. Deductions -42,242.95 -10,000.00 8. a.Contract Retentions -56,098.69 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 946,166.30 192,183.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 192,183.12