Dept. of Trans. PROGRESS Serial No. Contract No. 03-266-13-23 11-069104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-5-R19.4/R20.1 Federal Project: ACNH-X073(58) Progress payment No. 25 Payment period ending: 09-20-03 MARINA LANDSCAPE INC 1100 E KATELLA AVE ANAHEIM CA 92805 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,571,259.31 4,950.91 2.a. Extra Work 88,047.14 0.00 b. Adjustment Comp. -17,562.70 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,641,743.75 4,950.91 5. Mobilization 45,000.00 0.00 6. Total Work Completed 2,686,743.75 7. Deductions -6,000.00 -1,000.00 8. a.Contract Retentions -132,087.19 -247.55 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,548,656.56 3,703.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,703.36