Dept. of Trans. PROGRESS Serial No. Contract No. 04-113-13-56 11-069104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-5-R19.4/R20.1 Federal Project: ACNH-X073(58) Progress payment No. 32 Payment period ending: 04-20-04 MARINA LANDSCAPE INC 1100 E KATELLA AVE ANAHEIM CA 92805 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,605,362.73 4,302.40 2.a. Extra Work 92,514.73 0.00 b. Adjustment Comp. -17,562.70 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,680,314.76 4,302.40 5. Mobilization 45,000.00 0.00 6. Total Work Completed 2,725,314.76 7. Deductions -6,000.00 0.00 8. a.Contract Retentions -134,015.74 -215.12 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,585,299.02 4,087.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,087.28