Dept. of Trans. PROGRESS Serial No. Contract No. 01-234-14-46 11-070204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 6% 11-SD-94-3.7/4.6 Federal Project: ACIM-805-1(581) ACNH-S094(51) Progress payment No. 03 Payment period ending: 08-20-01 TERRA CAL CONSTRUCTION INC 14530 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 01773 Total Estimate This Estimate 1. Contract Itms Without Mobil. 308,427.47 195,023.19 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 308,427.47 195,023.19 5. Mobilization 101,583.75 101,583.75 6. Total Work Completed 410,011.22 7. Deductions -28,800.75 -20,000.00 8. a.Contract Retentions -30,842.75 -19,502.32 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 350,367.72 257,104.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 257,104.62