Dept. of Trans. PROGRESS Serial No. Contract No. 02-113-12-52 11-070204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 21% 11-SD-94-3.7/4.6 Federal Project: ACIM-805-1(581) ACNH-S094(51) Progress payment No. 11 Payment period ending: 04-20-02 TERRA CAL CONSTRUCTION INC 14530 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 01773 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,040,755.29 167,701.77 2.a. Extra Work 9,478.84 -283.12 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,050,234.13 167,418.65 5. Mobilization 135,445.00 0.00 6. Total Work Completed 2,185,679.13 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -102,511.71 -8,370.94 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,073,167.42 159,047.71 10. Reduction Amt to Escrow 11. Payment to Escrow 102,510.00 12. Net Pymt. this Estimate 159,047.71