Dept. of Trans. FINAL Serial No. Contract No. 06-061-09-09 11-070204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-94-3.7/4.6 Federal Project: ACIM-805-1(581) ACNH-S094(51) Progress payment No. 45 Payment period ending: 09-02-05 TERRA CAL CONSTRUCTION INC 40255 98TH STREET WEST LEONA VALLEY, CA 93551 Escrow No. 01773 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,651,568.53 0.00 2.a. Extra Work 40,322.56 0.00 b. Adjustment Comp. 2,100.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,693,991.09 0.00 5. Mobilization 135,445.00 0.00 6. Total Work Completed 2,829,436.09 7. Deductions 8. a.Contract Retentions -133,943.60 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 133,943.60 0.00 9. Total pay to Contractor 2,829,436.09 0.00 10. Reduction Amt to Escrow -133,940.00 0.00 11. Payment to Escrow 133,940.00 12. Net Pymt. this Estimate 0.00