Dept. of Trans. PROGRESS Serial No. Contract No. 08-142-14-35 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 38% 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 07 Payment period ending: 05-20-08 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,278,905.64 183,930.66 2.a. Extra Work 9,095.82 1,945.78 b. Adjustment Comp. -11,479.00 -11,479.00 3. Materials on Hand 4. Earned Subject to Retention 1,276,522.46 174,397.44 5. Mobilization 266,000.00 0.00 6. Total Work Completed 1,542,522.46 7. Deductions -20,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,522,522.46 174,397.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 174,397.44