Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-12-36 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 45% 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 08 Payment period ending: 06-20-08 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,459,270.14 180,364.50 2.a. Extra Work 10,925.06 1,829.24 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,458,716.20 182,193.74 5. Mobilization 266,000.00 0.00 6. Total Work Completed 1,724,716.20 7. Deductions -30,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,694,716.20 172,193.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 172,193.74