Dept. of Trans. PROGRESS Serial No. Contract No. 08-235-07-12 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 58% 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 10 Payment period ending: 08-20-08 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,950,256.24 191,136.00 2.a. Extra Work 21,234.52 6,665.36 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,960,011.76 197,801.36 5. Mobilization 266,000.00 0.00 6. Total Work Completed 2,226,011.76 7. Deductions -40,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,186,011.76 197,801.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 197,801.36