Dept. of Trans. PROGRESS Serial No. Contract No. 08-295-14-42 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 71% 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 12 Payment period ending: 10-20-08 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,478,503.14 289,071.90 2.a. Extra Work 26,898.75 217.55 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,493,922.89 289,289.45 5. Mobilization 280,000.00 0.00 6. Total Work Completed 2,773,922.89 7. Deductions -40,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,733,922.89 279,289.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 279,289.45