Dept. of Trans. PROGRESS Serial No. Contract No. 08-326-14-00 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 78% 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 13 Payment period ending: 11-20-08 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,587,090.64 108,587.50 2.a. Extra Work 55,676.71 28,777.96 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,631,288.35 137,365.46 5. Mobilization 280,000.00 0.00 6. Total Work Completed 2,911,288.35 7. Deductions -20,000.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,891,288.35 157,365.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 157,365.46