Dept. of Trans. PROGRESS Serial No. Contract No. 08-354-13-55 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 83% 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 14 Payment period ending: 12-20-08 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,797,920.14 210,829.50 2.a. Extra Work 59,313.47 3,636.76 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,845,754.61 214,466.26 5. Mobilization 280,000.00 0.00 6. Total Work Completed 3,125,754.61 7. Deductions -20,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,105,754.61 214,466.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 214,466.26