Dept. of Trans. PROGRESS Serial No. Contract No. 09-022-13-55 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 88% 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 15 Payment period ending: 01-20-09 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,057,470.04 259,549.90 2.a. Extra Work 61,271.41 1,957.94 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,107,262.45 261,507.84 5. Mobilization 280,000.00 0.00 6. Total Work Completed 3,387,262.45 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,377,262.45 271,507.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 271,507.84