Dept. of Trans. PROGRESS Serial No. Contract No. 09-055-14-09 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 94% 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 16 Payment period ending: 02-20-09 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,491,495.74 434,025.70 2.a. Extra Work 61,663.03 391.62 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,541,679.77 434,417.32 5. Mobilization 280,000.00 0.00 6. Total Work Completed 3,821,679.77 7. Deductions -5,000.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,816,679.77 439,417.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 439,417.32