Dept. of Trans. PROGRESS Serial No. Contract No. 09-083-14-07 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 100% 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 17 Payment period ending: 03-20-09 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,700,859.24 209,363.50 2.a. Extra Work 64,994.33 3,331.30 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,754,374.57 212,694.80 5. Mobilization 280,000.00 0.00 6. Total Work Completed 4,034,374.57 7. Deductions -11,000.00 -6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,023,374.57 206,694.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 206,694.80