Dept. of Trans. PROGRESS Serial No. Contract No. 09-167-14-04 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 20 Payment period ending: 06-20-09 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,757,116.24 9,880.00 2.a. Extra Work 133,940.64 16,206.88 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,879,577.88 26,086.88 5. Mobilization 280,000.00 0.00 6. Total Work Completed 4,159,577.88 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,154,577.88 26,086.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,086.88