Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-14-40 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 21 Payment period ending: 07-20-09 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,772,646.24 15,530.00 2.a. Extra Work 144,432.04 10,491.40 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,905,599.28 26,021.40 5. Mobilization 280,000.00 0.00 6. Total Work Completed 4,185,599.28 7. Deductions -3,553.00 1,447.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,182,046.28 27,468.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,468.40