Dept. of Trans. PROGRESS Serial No. Contract No. 09-295-13-54 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 24 Payment period ending: 10-20-09 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,854,726.24 47,070.00 2.a. Extra Work 162,864.73 0.00 b. Adjustment Comp. -11,479.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,006,111.97 47,070.00 5. Mobilization 280,000.00 0.00 6. Total Work Completed 4,286,111.97 7. Deductions -3,553.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,282,558.97 47,070.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 47,070.00