Dept. of Trans. PROGRESS Serial No. Contract No. 12-024-08-44 11-070404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-15-R3.2/M4.1 Federal Project: ACIM-X073(83) Progress payment No. 51 Payment period ending: 01-20-12 A C C U CONSTRUCTION INC 1526 BROOKHOLLOW DR, STE 76 SANTA ANA CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,136,479.84 9,530.00 2.a. Extra Work 189,370.80 0.00 b. Adjustment Comp. -10,652.63 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,315,198.01 9,530.00 5. Mobilization 280,000.00 0.00 6. Total Work Completed 4,595,198.01 7. Deductions -1,000.00 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,594,198.01 10,530.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,530.00