Dept. of Trans. PROGRESS Serial No. Contract No. 07-023-10-46 11-072804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 27% 11-SD-78-3.2/5.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 01-20-07 SIM J HARRIS INC P O BOX 420850 SAN DIEGO CA 921420850 Escrow No. 02272 Total Estimate This Estimate 1. Contract Itms Without Mobil. 214,569.80 35,147.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 214,569.80 35,147.80 5. Mobilization 6. Total Work Completed 214,569.80 7. Deductions -3,514.78 -3,514.78 8. a.Contract Retentions -21,456.98 -3,514.78 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 189,598.04 28,118.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,118.24